THEARC Construction Progress Update

The structural steel frame is nearly complete and interior masonry for stairs and elevators is underway. Concrete topping on elevated floor decks is in place in several locations and preparations for ground floor slab on grade are nearing completion. Installation of interior mechanical & plumbing work has begun in the basement. Look for exterior wall framing and sheathing to begin in the next few weeks.